8
8
The Quantity Schedule provides for double handrails to all platforms.
Toeboards have been included to one working platform only therefore
additional toeboards will have to be added to any other levels that are
used as working platforms and/ or for storage of materials.
Furthermore, product standards require that towers have platforms
placed at least every 4m. The Schedule exceeds this requirement.
The BETA tower will be built safely and therefore compliance with the
requirements of the Work at Height Regulations 2005 will also be met, if
the schedule is followed.
Ballast: Internal/ External Use
Ballast is not required on BETA towers if using stabilisers as detailed on
Quantity Schedule.
Quantity Schedule - 1450 3T Method
Note 200mm castors were used in the self weight calculations as
detailed in the Quantity Schedule on opposite page.
Maximum Safe Working Loads (S.W.L.)
300kg per platform evenly distributed.
900kg per tower evenly distributed.
The platform can consist of either one deck or two decks (placed side
by side).
The load MUST be evenly distributed over entire platform area (whether
one deck or two decks).
A maximum of 3 platform levels may be loaded.
The self weight of the tower components is not part of the 900kg S.W.L.
per tower and has already been taken into account.
Commenti su questo manuale